Princess Alexandra Hospital
Since 2020 we have worked with the Trust to deliver a ground breaking 10 schemes. 10 schemes in 14 months.
Project
Princess Alexandra Hospital
Client
Princess Alexandra Hospital
Value
£14M
Contract
Healthcare; 10 Schemes In 14 Months
Site Programme
18 months
We were engaged with Princess Alexandra Hospital since the summer of 2020, with our first project starting on site in October 2020. Since then we have worked with the Trust to deliver a ground breaking 10 schemes.
Our approach to working together and our accelerated works processes, have meant that from the 1 project we were initially procured for, we were then selected to complete a further 9 more.
Many of the projects were born out of the Hospital facing unprecedented pressures in terms of patient numbers and how efficiently they could be reviewed. This was an issue pre covid, but during the pandemic this issue was exacerbated.
With the new modern hospital still in the design process, the build and readiness for patients is many years to come; the Trust needs to address several areas of existing Hospital to make it fit for purpose now.
This has covered:
- Updating wards to modern day medical grade standards.
- Improving layouts and creating efficiencies for different patient types.
- Providing additional space due to distancing measures.
“The Actiform project team worked ‘hand in hand’ with their design team to create a future focused build that rethinks the way a NHS trust delivers modular construction within a conventional aging and varied built environment, and that is integrated into the core operation of the hospital. The completed build environment was an integral part of the overall strategy for the new emergency care services.”
Pasqualino Risi
Associate Director of Estates and Facilities
Adult Assessment Unit
Duration
12 Weeks / 16 Weeks
A two-storey extension, completed over 2 phases. Initially to support the pandemic, with non-covid patients, long term it will provide a dedicated space to see patients for rapid assessment and treatment for a variety of illnesses and injuries.
CT Scanner Module
Duration
12 Weeks
The introduction of the CT Scanner facility improves the turnaround time and increases the flow of urgent care patients through the hospital. This specially designed module is lead lined and is linked directly with the Frailty Assessment Unit.
Winter Ward
Duration
12 Weeks
At Actiform we also provide traditional building services. At PAH we are providing strip out and fit out of wards, to bring them up to current medical grade standards. Penn Ward was the first ward we have refurbished.
Saunders Ward
Duration
10 Weeks
Following the refurbishment of Penn Ward and Winter Ward we are now conducting a refurbishment of Saunders Ward. This accelerated works package allows for minimum disruption and quick turnaround of much needed ward space at the Hospital.
Medical Records Store
Duration
4 Weeks
The Medical Records Store at the Hospital was relocated due to the reconfiguration of space within the hospital due to COVID. A new highly secure and fit for purpose module was introduced with a link to the main hospital building, to house the sensitive records.
Frailty Unit
Duration
14 Weeks
The Frailty Assessment Unit is an integral part of the Hospital providing care for frail patients generally those aged 75 years
or above. Created based on the demand for winter patients, the short stay facility alleviates pressures from other areas
of the Hospital.
Alex Lounge & Agile Workspace
Duration
14 Weeks
This project which is currently on site is delivering much needed additional space for the restaurant area. It will also provide
a much-needed rest-bite area for staff who have delivered long shifts, including a multi-use room where they can relax including a yoga space.
Training & Education Centre
Duration
20 Weeks
Our most recent project; a fast track, non- modular scheme using SIP technology which is being constructed beneath an existing Ward. This training facility will replicate exact specifications of real Theatre and Ward spaces, including frontline technologies.