Princess Alexandra Hospital – Refurbishments
Although not modular, Actiform have also completed multiple refurbishment projects for both Public and Private sector Healthcare clients.
Project
Refurbishments
Client
Princess Alexandra Hospital
Contract
Refurbishments
Site Programme
10 weeks
Our project manager worked directly with the Client team at Harlow to develop a detailed program of works, taking into consideration every stage of the project and daily activities on site. This involved working with the Trusts AP’s to develop a safe method of isolation to enable the works to commence.
Our Mechanical and electrical teams then worked together with Actiform as a single team to deliver the project.
Design
Meetings were set up between our in-house Design Team and the M&E Design teams in order to be clear on the expectations required from each party and confirm the understanding of the client requirements.
The Mechanical and Electrical designs were produced by our contractors and approved by Actiform prior to being submitted to the client for comment and sign off.
Any requested derogations from HTM were clearly outlined and recorded. Once agreed, we overlayed the M&E designs onto our existing CAD drawing and checked for any clashes. Once approved by the Technical Design Manager, the design was submitted to the Client for approval.
The Works
During the installation process our Site and Project manager quality checked the installations of both M&E contractors, ensuring that the standards we expect were being achieved. Photographic evidence of mechanical and electrical services including containment and fire stopping were collated throughout the project.
Upon commissioning all documentation including “as built” were delivered along with the Bolster report for fire stopping.